Tuesday, August 28, 2018

Building a House: Part 3 Foundation

Seeing the forms go up was an exciting day. It was neat to see how the house would actually lay on the land; it started to become real.



Plumbing getting set:









Rebar! Our slab was engineered as a post tension slab.






And we have concrete! Here is the garage.


Front door will be here:



This is about 4500 sqft of concrete. Justin is standing in his future walk in shower.


Monday, August 27, 2018

Building a House: Part 2 Dirt Work and Foundation Prep

Our soil is sandy loam with an emphasis on sandy. Between the sand and the slope, it took over 1200 yards of dirt trucked in to build up the soil to prepare it for the foundation.














Another before and after. Quite a difference.



Sunday, August 26, 2018

Building a House: Part 1 Clearing the Land

We had to do a lot of clearing for the spot we decided to build the house at. It is situated behind the cabin and a little bit closer to the front road, just due to the natural slope our property has and to eliminate having to cut down a bunch of oak trees. The way we ended up situating the house we only had to cut down 1 oak, everything else we mulched or cut down were cedars. We ended up paying somebody with a hydro mulch to come in and clear all the underbrush and shred several trees. Then Justin cut down a bunch more trees and we hired some guys to clean those logs up and stack them. 

Here is the land before any work was really done:





And here is the same area after the first day with the hydro mulcher (it took a few days to do it all):










Here is before (below) and after (above) picture from the same spot:




All that red are mulched cedar trees. It was extremely fragrant.



A few more before and after compilations:










SO MUCH MULCH! You can see all the trees that disappeared in this before and after:




We sold a good amount of these logs to a lumber mill and had our fireplace mantel made from one of them too.


Some of the root balls we need to burn at some point.


All cleared and broken through the front tree line so trucks can get back here. This one burn pile went on for a good week.


A Long Hiatus

After over a year of no posts, I am finally going to catch up with everything that has been going on. Because we have been BUSY.

Kids:

Levi started Kindergarten last year and is now in first grade. He participated in Fall and Spring Soccer, was taking piano lessons and sewing lessons. He did 2 weeks of art camp and VBS this summer. He's about to be in Fall Soccer again.

Mattie started Kindergarten this year, has been doing gymnastics for the past year and a half plus, sewing lessons, and is going to try soccer this Fall. She got to do VBS again this summer and enjoyed it.

Hailey is now 2, very talkative and very funny. She is quite animated and dramatic and keeps us all laughing. We are trying to encourage potty training and have Peppa Pig big girl britches to try and entice her. She is adamant that she is the baby and is NOT a big girl.

Justin and me (Rachel):

Justin is still busy with work but took off several weeks for the first time ever this month. He and I went on a week long vacation (sans kids) to Oregon to celebrate our 10 year anniversary. I have also been busy as the treasurer of our church (volunteer), our church representative to the Ministerial Alliance in town, and the treasurer for Episcopal Church Women (ECW). And I still have paying clients that I do bookkeeping for - and continue to get new clients. And in the midst of doing all this, we started building a house.

The House:

We met with the bank in July of last year to even determine if it was possible to begin building our dream home. It was! So I drew up the floorplan (not to scale) and took them to my mother in law, who drew them up professionally to scale. I took her plans to an architect and had them officially done. They only changed a little bit from my initial concept. Then, we started trying to get bids from custom builders - which took forever because that was in August of last year - right when Hurricane Harvey hit. But we finally settled on a builder, closed on the loan in January of this year, and after weeks of rain delays, finally got started. More on this to follow in additional posts.